Skip to main content

Nitrogen+Syngas 369 Jan-Feb 2021

Plant Manager+


UREAKNOWHOW.COM INCIDENT REPORT

Plant Manager+

Incident Nos. 4 & 5 Leak detection system failures in urea plants

The following case studies describe serious incidents associated with leak detection system failures. Incident 4 relates to the failure of the active pressurised leak detection system for the loose liner of a urea reactor and Incident 5 relates to a passive leak detection system which failed to work leading to serious corrosion of the carbon steel wall of the HP scrubber.

Incident No. 4

Event description

During a daily routing plant tour the plant operator observed a crystallised white product deposited on the insulation sheeting of the urea reactor which worsened quite quickly over time. Some ammonia vapour was also noticed.

Immediate response action

Initially a leak at the manway cover was assumed, since the active pressurised leak detection system was not indicating any leak. A closer look, however, indicated a possible leak in the liner and so the plant was stopped for inspection.

Causes

The installed active pressurised leak detection system failed to warn operations. The pinhole leak in the liner had created severe corrosion attack of the carbon steel pressure shell and the reactor was taken out of service just in time. The state-of-the-art leak detection had failed to indicate the leak due to a combination of wrong commissioning of the system and failure of some components, as well as insufficient inspection and maintenance of the system.

Primary consequence

There was a near miss of the high pressure vessel rupturing.

Secondary consequence

The incident led to an unplanned shutdown. A temporary repair was carried out initially, with a full repair executed within one year.

Prevention safeguards

Assure proper functioning of the leak detection system. Safe operation of the plant is only possible with a good working leak detection system.

Mitigation safeguards

In case of a leak, confirm and locate the leak, shut down the plant and drain the synthesis section as soon as possible.

Corrective recommendation The leak detection system was refurbished and made operational before start-up of the plant. In addition, an inspection and maintenance program was implemented to increase the reliability and availability of the existing leak detection system. All plant operators received further training.

Incident No. 5

Event description

In February 2018, a leak was visible in the spherical dome part of a HP scrubber of a 1,750 t/d Stamicarbon COstripping urea plant. The plant was shut down.

Upon opening of the HP scrubber sphere it became clear that severe corrosion had occurred on the 316L UG liners. The liner was covered with a large amount of corrosion products and many cracks were visible. The cracks had resulted in leaks that had gone unnoticed by the passive leak detection system, likely due to clogging. Therefore, corrosion of the carbon steel pressure part commenced undetected. Many cracks were also found in the carbon steel wall and grooves and holes were partly blocked by corrosion products.

Immediate response action

The plant was stopped to attend the leak.

Causes

In the passive leak detection system it takes too long for the leak to show up at the analyser. The leaks in the liner had already clogged the tubing (the leaks were cracks).

Primary consequence

A rupture of the high pressure vessel was avoided by luck.

Secondary consequence

There was an unplanned shutdown of about two months for extensive work to repair the HP scrubber.

Risk level

The likelihood of a major consequence was moderate, but the risk level was high.

Risk level The likelihood of a major consequence was moderate, but the risk level was high.

Prevention safeguards

Assure proper functioning of the leak detection system. Safe operation of the plant is only possible with a good working leak detection system, including an accurate and reliable ammonia analyser.

Mitigation safeguards

In case of a leak, confirm and locate the leak, shut down the plant and drain the synthesis section as soon as possible.

Corrective recommendation

The leak detection system was refurbished and made operational before start-up of the plant. In addition, an inspection and maintenance program was implemented to increase the reliability and availability of the existing leak detection system. All plant operators received further training.

Latest in Outlook & Reviews

Tariff uncertainties cloud the picture

Nitrogen+Syngas went to press just a few days before Donald Trump’s swearing-in as the next president of the United States. While it is sometimes difficult to sort the truth from the hyperbole in his public pronouncements, nevertheless, if taken at face value, they would seem to indicate that we may be in for a turbulent four years in commodity markets in particular. While he is an avowed military non-interventionist, on the economic policy side he has emerged as a firm believer in the power of tariffs to alter markets in the favour of the US, and has promised 20% tariffs on all goods entering the US, potentially rising to 25% for Canada and Mexico, and 60% for his particular bugbear, China, sparking a scramble for wholesalers to stock up in the last few weeks of the Biden presidency. Trump previously raised tariffs on Chinese goods entering the US to 20% during his first term, and the Biden administration made no attempt to reverse this, and even added some additional ones, for example 20% on Russian and Moroccan phosphate imports.